In a very short period of time Sheet Piles were finished successfully. More than 100 piles were prepared for the cap beam construction. Our mold and rebar teams work for the cap beam for pouring concrete. And in a week we finished the cap beam construction too.

After excavation of the foundation we will start the pile digging.